6. Economic Evaluation of Facility Investments
6.1 Project Life Cycle and Economic Feasibility
Facility investment decisions represent major commitments of corporate resources and have serious consequences on the profitability and financial stability of a corporation. In the public sector, such decisions also affect the viability of facility investment programs and the credibility of the agency in charge of the programs. It is important to evaluate facilities rationally with regard to both the economic feasibility of individual projects and the relative net benefits of alternative and mutually exclusive projects.
This chapter will present an overview of the decision process for economic evaluation of facilities with regard to the project life cycle. The cycle begins with the initial conception of the project and continues though planning, design, procurement, construction, start-up, operation and maintenance. It ends with the disposal of a facility when it is no longer productive or useful. Four major aspects of economic evaluation will be examined:
1. The basic concepts of facility investment evaluation, including time preference for consumption, opportunity cost, minimum attractive rate of return, cash flows over the planning horizon and profit measures.
2. Methods of economic evaluation, including the net present value method, the equivalent uniform annual value method, the benefit-cost ratio method, and the internal rate of return method.
3. Factors affecting cash flows, including depreciation and tax effects, price level changes, and treatment of risk and uncertainty.
4. Effects of different methods of financing on the selection of projects, including types of financing and risk, public policies on regulation and subsidies, the effects of project financial planning, and the interaction between operational and financial planning.
It is important to distinguish between the economic evaluation of alternative physical facilities and the evaluation of alternative financing plans for a project. The former refers to the evaluation of the cash flow representing the benefits and costs associated with the acquisition and operation of the facility, and this cash flow over the planning horizon is referred to as the economic cash flow or the operating cash flow. The latter refers to the evaluation of the cash flow representing the incomes and expenditures as a result of adopting a specific financing plan for funding the project, and this cash flow over the planning horizon is referred to as the financial cash flow. In general, economic evaluation and financial evaluation are carried out by different groups in an organization since economic evaluation is related to design, construction, operations and maintenance of the facility while financial evaluations require knowledge of financial assets such as equities, bonds, notes and mortgages. The separation of economic evaluation and financial evaluation does not necessarily mean one should ignore the interaction of different designs and financing requirements over time which may influence the relative desirability of specific design/financing combinations. All such combinations can be duly considered. In practice, however, the division of labor among two groups of specialists generally leads to sequential decisions without adequate communication for analyzing the interaction of various design/financing combinations because of the timing of separate analyses.
As long as the significance of the interaction of design/financing combinations is understood, it is convenient first to consider the economic evaluation and financial evaluation separately, and then combine the results of both evaluations to reach a final conclusion. Consequently, this chapter is devoted primarily to the economic evaluation of alternative physical facilities while the effects of a variety of financing mechanisms will be treated in the next chapter. Since the methods of analyzing economic cash flows are equally applicable to the analysis of financial cash flows, the techniques for evaluating financing plans and the combined effects of economic and financial cash flows for project selection are also included in this chapter.
Back to top
6.2 Basic Concepts of Economic Evaluation
A systematic approach for economic evaluation of facilities consists of the following major steps:
1. Generate a set of projects or purchases for investment consideration.
2. Establish the planning horizon for economic analysis.
3. Estimate the cash flow profile for each project.
4. Specify the minimum attractive rate of return (MARR).
5. Establish the criterion for accepting or rejecting a proposal, or for selecting the best among a group of mutually exclusive proposals, on the basis of the objective of the investment.
6. Perform sensitivity or uncertainty analysis.
7. Accept or reject a proposal on the basis of the established criterion.
It is important to emphasize that many assumptions and policies, some implicit and some explicit, are introduced in economic evaluation by the decision maker. The decision making process will be influenced by the subjective judgment of the management as much as by the result of systematic analysis.
The period of time to which the management of a firm or agency wishes to look ahead is referred to as the planning horizon. Since the future is uncertain, the period of time selected is limited by the ability to forecast with some degree of accuracy. For capital investment, the selection of the planning horizon is often influenced by the useful life of facilities, since the disposal of usable assets, once acquired, generally involves suffering financial losses.
项目管理之路二(doc)
6. Economic Evaluation of Facility Investments
6.1 Project Life Cycle and Economic Feasibility
Facility investment decisions represent major commitments of corporate resources and have serious consequences on the profitability and financial stability of a corporation. In the public sector, such decisions also affect the viability of facility investment programs and the credibility of the agency in charge of the programs. It is important to evaluate facilities rationally with regard to both the economic feasibility of individual projects and the relative net benefits of alternative and mutually exclusive projects.
This chapter will present an overview of the decision process for economic evaluation of facilities with regard to the project life cycle. The cycle begins with the initial conception of the project and continues though planning, design, procurement, construction, start-up, operation and maintenance. It ends with the disposal of a facility when it is no longer productive or useful. Four major aspects of economic evaluation will be examined:
1. The basic concepts of facility investment evaluation, including time preference for consumption, opportunity cost, minimum attractive rate of return, cash flows over the planning horizon and profit measures.
2. Methods of economic evaluation, including the net present value method, the equivalent uniform annual value method, the benefit-cost ratio method, and the internal rate of return method.
3. Factors affecting cash flows, including depreciation and tax effects, price level changes, and treatment of risk and uncertainty.
4. Effects of different methods of financing on the selection of projects, including types of financing and risk, public policies on regulation and subsidies, the effects of project financial planning, and the interaction between operational and financial planning.
It is important to distinguish between the economic evaluation of alternative physical facilities and the evaluation of alternative financing plans for a project. The former refers to the evaluation of the cash flow representing the benefits and costs associated with the acquisition and operation of the facility, and this cash flow over the planning horizon is referred to as the economic cash flow or the operating cash flow. The latter refers to the evaluation of the cash flow representing the incomes and expenditures as a result of adopting a specific financing plan for funding the project, and this cash flow over the planning horizon is referred to as the financial cash flow. In general, economic evaluation and financial evaluation are carried out by different groups in an organization since economic evaluation is related to design, construction, operations and maintenance of the facility while financial evaluations require knowledge of financial assets such as equities, bonds, notes and mortgages. The separation of economic evaluation and financial evaluation does not necessarily mean one should ignore the interaction of different designs and financing requirements over time which may influence the relative desirability of specific design/financing combinations. All such combinations can be duly considered. In practice, however, the division of labor among two groups of specialists generally leads to sequential decisions without adequate communication for analyzing the interaction of various design/financing combinations because of the timing of separate analyses.
As long as the significance of the interaction of design/financing combinations is understood, it is convenient first to consider the economic evaluation and financial evaluation separately, and then combine the results of both evaluations to reach a final conclusion. Consequently, this chapter is devoted primarily to the economic evaluation of alternative physical facilities while the effects of a variety of financing mechanisms will be treated in the next chapter. Since the methods of analyzing economic cash flows are equally applicable to the analysis of financial cash flows, the techniques for evaluating financing plans and the combined effects of economic and financial cash flows for project selection are also included in this chapter.
Back to top
6.2 Basic Concepts of Economic Evaluation
A systematic approach for economic evaluation of facilities consists of the following major steps:
1. Generate a set of projects or purchases for investment consideration.
2. Establish the planning horizon for economic analysis.
3. Estimate the cash flow profile for each project.
4. Specify the minimum attractive rate of return (MARR).
5. Establish the criterion for accepting or rejecting a proposal, or for selecting the best among a group of mutually exclusive proposals, on the basis of the objective of the investment.
6. Perform sensitivity or uncertainty analysis.
7. Accept or reject a proposal on the basis of the established criterion.
It is important to emphasize that many assumptions and policies, some implicit and some explicit, are introduced in economic evaluation by the decision maker. The decision making process will be influenced by the subjective judgment of the management as much as by the result of systematic analysis.
The period of time to which the management of a firm or agency wishes to look ahead is referred to as the planning horizon. Since the future is uncertain, the period of time selected is limited by the ability to forecast with some degree of accuracy. For capital investment, the selection of the planning horizon is often influenced by the useful life of facilities, since the disposal of usable assets, once acquired, generally involves suffering financial losses.
项目管理之路二(doc)
[下载声明]
1.本站的所有资料均为资料作者提供和网友推荐收集整理而来,仅供学习和研究交流使用。如有侵犯到您版权的,请来电指出,本站将立即改正。电话:010-82593357。
2、访问管理资源网的用户必须明白,本站对提供下载的学习资料等不拥有任何权利,版权归该下载资源的合法拥有者所有。
3、本站保证站内提供的所有可下载资源都是按“原样”提供,本站未做过任何改动;但本网站不保证本站提供的下载资源的准确性、安全性和完整性;同时本网站也不承担用户因使用这些下载资源对自己和他人造成任何形式的损失或伤害。
4、未经本网站的明确许可,任何人不得大量链接本站下载资源;不得复制或仿造本网站。本网站对其自行开发的或和他人共同开发的所有内容、技术手段和服务拥有全部知识产权,任何人不得侵害或破坏,也不得擅自使用。
我要上传资料,请点我!
管理工具分类
ISO认证 课程讲义 管理表格 合同大全 法规条例 营销资料 方案报告 说明标准 管理战略 商业计划书 市场分析 战略经营 策划方案 培训讲义 企业上市 采购物流 电子商务 质量管理 企业名录 生产管理 金融知识 电子书 客户管理 企业文化 报告论文 项目管理 财务资料 固定资产 人力资源 管理制度 工作分析 绩效考核资料 面试招聘 人才测评 岗位管理 职业规划 KPI绩效指标 劳资关系 薪酬激励 人力资源案例 人事表格 考勤管理 人事制度 薪资表格 薪资制度 招聘面试表格 岗位分析 员工管理 薪酬管理 绩效管理 入职指引 薪酬设计 绩效管理 绩效管理培训 绩效管理方案 平衡计分卡 绩效评估 绩效考核表格 人力资源规划 安全管理制度 经营管理制度 组织机构管理 办公总务管理 财务管理制度 质量管理制度 会计管理制度 代理连锁制度 销售管理制度 仓库管理制度 CI管理制度 广告策划制度 工程管理制度 采购管理制度 生产管理制度 进出口制度 考勤管理制度 人事管理制度 员工福利制度 咨询诊断制度 信息管理制度 员工培训制度 办公室制度 人力资源管理 企业培训 绩效考核 其它
精品推荐
- 1XX公司战略发展目标(xls 518
- 2“回佣”管理规定 844
- 3通信公司战略的制定方法(pp 570
- 4500强企业管理方法(ppt 946
- 5管理沟通172页(doc) 772
- 6农村基层人才现状的调查与思考 569
- 7企业内部控制应用指引—资产管 912
- 8新创企业的风险管理.ppt 586
- 9逐条点评《劳动合同法实施条例 732
下载排行
- 1社会保障基础知识(ppt) 16695
- 2安全生产事故案例分析(ppt 16695
- 3行政专员岗位职责 16695
- 4品管部岗位职责与任职要求 16695
- 5员工守则 16695
- 6软件验收报告 16695
- 7问卷调查表(范例) 16695
- 8工资发放明细表 16695
- 9文件签收单 16695